198805315 - Hood River Adult Salmonid Trapping Facilities/Parkdale Fish Facility Expansion

Sponsor: Oregon Department of Fish & Wildlife (ODFW)

Budgets: FY07: $750,000 | FY08: $250,000 | FY09: $150,000

Short description: Conduct environmental compliance and initiate construction on proposed adult salmonid trapping facilities in the Hood River Subbasin, and expansion of the Parkdale Fish Facility to accommodate spring Chinook rearing.

view full proposal

Final Council recommendation (Nov 2006)

Funding category: Expense

Recommended budgets: FY07: $0 | FY08: $0 | FY09: $0

Comment:

ISRP final recommendation: Not fundable

Comment:

Despite its numeric designation as an ongoing project, this seems to be new work and appropriate for the Three-Step Review process. As written, the proposal suffered greatly from a lack of clarity and definition in every aspect. The ISRP cannot recommend this project for funding at this time.

Response loop edit

See the sponsor's revised proposal from the response loop. You'll be taken to CBFWA's proposal system in Section 10 where most sponsors uploaded revised narratives or other responses to the ISRP comments.

State/province recommendation: Fundable when money available

Review group: OSPIT - Gorge

Recommended budgets: FY07: $0 | FY08: $0 | FY09: $0

Comment: OSPIT concurs with ISRP that this project should go into the Three Step process and so we have removed money for implementation. However, given that Powerdale Dam is slated for removal in 2010, it is imperative that the proposal for reconfiguring the trapping facilities get reviewed in the Step process during this funding cycle.